Location
Gwadar, Balochistan
Sector
Public Health
Total Cost
PKR 8.2B
Year
2023
Client
Gwadar Development Authority
Project Background
Gwadar Development Authority (GDA), under the umbrella project “Necessary Facilities of Fresh Water Treatment, Water Supply & Distribution Gwadar” with an approved PC-1 cost of Rs. 11,322.00 million, is facilitating the population of the city. The Project is being executed in different phases. Phase-I: Design & Construction Supervision of the 7.5 MGD Water Transmission Main from Swad Dam to Gwadar City, comprising HDPE pipelines of 710 mm (50 km) and 630 mm (20 km), a 6.5 MGD underground water storage tank and three pumping stations, along with surface reservoirs and a chlorination tank. Phase-II: Design & Construction Supervision of the 2.5 MGD Water Transmission Main from Shadi Kaur Dam to Chaud Daggar, with an 84 km HDPE pipeline (500 mm) and two pumping stations. Phase-III: Design & Construction Supervision of the 5 MGD Water Supply Distribution System & Sewerage Network for Gwadar City, with 140 km of HDPE water pipelines (90–500 mm), 18.4 km of sewer pipes (300–500 mm) and four pumping stations.
Services
- Topographic Survey
- Geotechnical Investigation
- Pipeline Design using Various Diameters Depending on Flow
- Hydraulic Modelling
- Design of UG Tanks, Pumping Stations, Surface Reservoirs and Chlorination Tanks
- Preparation of Tender Documents
- Detailed Resident Supervision