Location
Multan
Sector
Roads & Highways
Total Cost
PKR 7.8B
Year
2015
Client
National Highway Authority
Project Background
The Project aims at easing the traffic congestion of Multan City. The project involves the Design & Construction Supervision of Inner City Ring Road Multan (Package – I, II & III) / interchanges including approach roads. Package-I: Construction of Flyover at Jinnah Chowk & Rasheedabad Chowk; Package-II: Construction of Flyover at Chungi # 08 & 09 with bridge length ranging from 225m – 685m. Package-III: Construction of Flyover at Kalma Chowk & Double Phattak with bridge length ranging from 160m – 300m.
Services
- Topographic surveys, cross-sections and contouring
- Traffic surveys, projections and forecasting
- Hydrology, drainage and alignment studies
- Design of pavements, flyovers and approach roads
- Soil, material and geotechnical studies
- Construction drawings and preliminary / final design reports
- Engineer's estimates, tender documents, BOQs and specifications
- Supervision of earthworks, mix designs, pavements, bridges and retaining structures
- Quality control, testing, progress reporting and bill verification