Location
Port Qasim, Karachi
Sector
Industrial
Total Cost
PKR 26B
Area
1,500 Acres
Year
2027
Client
Pakistan Industrial Development Corporation (Pvt.) Ltd., Ministry of Industries & Production
Project Background
Pakistan Industrial Development Corporation (PIDC) intends to setup an international standard Special Economic Zone in Karachi on an initial area of 1500 Acres, equipped with all amenities / utilities at the doorstep for the investors in a plug-and-play environment. The utilities will include all wet and dry utilities required for an industrial estate alongside its own 132 KV Grid Station. The proposed location is near Port Qasim at the land of Pakistan Steel Mills. The project aims to encourage foreign and domestic investors with diversified needs to setup industrial units, preferably oriented towards exports and imports substitution.
Services
EA’s scope of services included complete design and engineering solutions for bridge structure and infrastructure development. This covered feasibility analysis, structural design, geotechnical investigations, and construction supervision. Specialized expertise was applied in steel arch design, load testing, and quality assurance to ensure durability and safety. EA also coordinated with international consultants to align technical standards and project execution with global best practices.
- Topographic Survey
- Soil / Geotechnical Investigations
- Feasibility Study
- Structural Design
- Electro-Mechanical (MEP) Design
- Public Health Design
- External Development Design
- Preparation of PC-I Document
- Preparation of Contract Documents
- Pre-construction Services
- Construction Management and Supervision