Location
Punjab
Sector
Roads & Highways
Total Cost
PKR 148.7B
Year
2022
Client
National Highway Authority
Project Background
The Government of Pakistan undertook the construction of the Peshawar–Karachi Motorway, including the Lahore–Abdul Hakeem Section, a 230 km long, six-lane, controlled-access motorway executed under EPC mode. The project was financed through Government of Pakistan arrangements and implemented in accordance with FIDIC EPC Conditions of Contract. The National Highway Authority (NHA), as Employer, engaged the services of an Assistant to the Employer’s Representative (AER) to support project execution. The AER assisted the Employer in reviewing the detailed engineering designs prepared by the EPC Contractor, carried out overall supervision of the Contractor’s supervisory consultant, validated milestones for payments, and verified selected tests during construction and at completion. These services ensured that the motorway was delivered in compliance with the prescribed specifications, standards, and quality requirements for an ITS-enabled motorway.
Services
- Review of surveys, geotechnical, traffic, hydrology, materials and geological studies
- Review of geometric design, bridges, pavements, culverts, ITS, toll plazas and rest areas
- Review of traffic management plans, drawings and BOQs / estimates
- Review of contractors’ programmes, schedules and drawings
- Contract compliance and oversight of construction supervision
- Motorway operations and highway safety audits Monitoring during operation and maintenance